11-UT-004: Install North Ramp Water Distribution

Customer: Core Tech International

Location: AAFB,Guam

Start: September 2011

Complete: March 2013

Scope of Work:

  •   Excavate trench, 4000 CY
  •   Install 12” water pipe, C-900 DR18, gasket joint; 15051 LF
  •   Install 8” water pipe, C-900 DR18, gasket joint; 400 LF
  •   Install 6” water pipe, C-900 DR18, gasket joint; 2000 LF
  •   Install 4” water pipe, C-900 DR18, gasket joint; 160 LF
  •   Install 12” gate valve, UL/FM approved, NRS, MJ ends; 50 each
  •   Install 8” gate valve, UL/FM approved, NRS, MJ ends; 4 each
  •   Install 6” gate valve, UL/FM approved, NRS, MJ ends; 48 each
  •   Install 4” gate valve, UL/FM approved, NRS, MJ ends; 3 each
  •   Install cast iron valve box frame, 105 each
  •   Install 12” post indicator gate valve, UL/FM approved, NRS, MJ ends; 2 each
  •   Install 6” wet barrel fire hydrant assemblies, UL/FM approved; 48 each
  •   Install air release valve; 1 each
  •   Install bedding sand, 2500 CY
  •   Backfill and compact trench, 1500 CY
  •   Remove and dispose excess soil, 3000 CY