12-RW-005: Construct Curb, Gutter and Walkways to Chapel Road

Contractor: DZSP 21

Location: Naval Base, Guam

Start: March 2012

Complete: April 2012

Scope of Work: Demolish the existing concrete curb about 85LF and existing concrete slab, 12′ x 30′ and dispose. Excavate for gutter, curb and walkway approximately 39.75CY. Place and compact base course for curb, gutter and walkway approximately.