Contractor: DZSP 21
Location: B-3006, MESG-1 DET, Naval Base, Guam
Start: March 2012
Complete: April 2012
Scope of Work: Pull-out existing tarp to give access for tent frame canopy extension. Use 4″0 black pipe, schedule 20 for frame extension approximately 1 OLF for tent front and rear. All joint shall be full welded. Paint the new tent frame extension same color as the existing. Re-install the canopy using the existing tarp.