Contractor: DZSP21
Location: from Chapel Road to MWR Facility, Naval Base, Guam
Start: April 2012
Complete: May 2012
Scope of Work: Water-blast existing sidewalk, approximately 402LF x 8’wide. Repair crack on sidewalk with total length of 200LF. Replace damage concrete sidewalk 1ea. 4’wide x 12’long and 4ea. 2’wide x 8′ long.