13-DE-004: B21000 Demolition

Project: B21000 Demolition

Customer: P & S Construction, Inc

Location: B21000 Andersen Air Force Base, Guam

Start: September 2013

Complete: January 2014

Scope of Work:

The complete structural demolition of B21000, inclusive of temporary construction fence, dust control, All CMU/Concrete/Gypsum Walls, All Acousitcal Ceiling System, All flooring including exterior sidewalk, Roof/2nd Floor/Ground Floor Concrete Slabs, Stair Cases and Sanitary lines.

Restoration Scope: CMU Walls Installation, Stucco Wall Finish and Exterior Painting, Loam and Seeding (Top Soil, 6″ Thick, Grass Seedling)