13-MA-026: Inspect and Repair All Window and Door Seals to Ensure Proper Seal

Contractor: DZSP21

Location: BUILDING 10, MWR Child Development Center, Naval Hospital, Guam

Start: February 2013

Complete: February 2013 

Scope of Work:

Window Re-Sealing: Check existing windows for sealant crack if found, carefully take-out the defective sealant. Another option to check water leakage is to use a water hose connected to the facility water supply. This will be done one window at a time. The number of affective windows is 22 each.Carefully apply NP1 sealant to the affected window edges and scrape excess sealant.